November 14, 2025 Chungju Daehwa Mine Project Progress
페이지 정보

본문
Considering the discharge height required for aggregates and stone dust conveyed from the primary and secondary vibrating feeders through the primary cone crusher to the temporary stockyard, the belt conveyor discharge point was installed at an elevated height of approximately 5–6 meters.
Custom-cut support columns were fabricated and installed beneath the conveyor,
with the lower ends embedded into the ground for enhanced structural stability.
Additionally, a protective cover was installed at the conveyor inlet to prevent external spillage of aggregate materials.